I Understand that having a steel structure in mind, if the analytical model is created in robot, the following workflow should be used:
1. Creation of analytical model in Robot.
2. Creation of steel connections in Robot.
3. Creation of concrete elements in Robot.
2. The analytical model is sent to Revit.
3. The physical model (steel and concrete elements) is MANUALLY created in Revit, using the analytical model as a background (no automation available).
4. Each steel connection is created in Revit from scratch. Each steel connection tab must be opened in Robot and be visually copied in order to be created it in Revit.
5. The concrete reinforcement for every concrete element is created in Revit from scratch. Each reinforcement tab must be opened in Robot and be visually copied in order to be created in Revit.
7. Foundation elements are also created from scratch, with zero information transferred from Robot.
Is the above description correct?