Managing revisions in Revit

Managing revisions in Revit

Anonymous
Not applicable
13,777 Views
12 Replies
Message 1 of 13

Managing revisions in Revit

Anonymous
Not applicable

How can we manage revisions in Revit? We have more than 800 revisions in our project. Please note that we use revision per sheet option.

Please reply as soon as possible.

0 Likes
Accepted solutions (3)
13,778 Views
12 Replies
Replies (12)
Message 2 of 13

ToanDN
Consultant
Consultant
Using Revit Revisions and Revision schedule?
0 Likes
Message 3 of 13

Anonymous
Not applicable

Yes I am using Revision schedule in our Title Block.

0 Likes
Message 4 of 13

ToanDN
Consultant
Consultant
Great! Then how many of the 800 revisions do you need to show in the
schedule?
0 Likes
Message 5 of 13

Anonymous
Not applicable

I have the same problem, how can I downsize my Revison? so I only can see the 5 lates revision on my sheets instead of all the old revions I made. 

 

I know you can show "Current Revision" with the help of "Title block", so that the update version only show on the sheets.

 

Would be great if somebody could help me with this problem, been searching everywhere how to solve it.

 

 

0 Likes
Message 6 of 13

ToanDN
Consultant
Consultant
The revision schedule can be set to only show a fixed number of rows. You can open the OOTB title block, edit the revision schedule, look at the Appearance tab, and see how it was setup.
0 Likes
Message 7 of 13

Anonymous
Not applicable
How to get access to revision schedule? Please help.
0 Likes
Message 8 of 13

ToanDN
Consultant
Consultant
Open the title block family, select​ the revision schedule header, or open it from the browser.
Message 9 of 13

Viveka_CD
Alumni
Alumni
Accepted solution

Hi @Anonymous

  • You can track your revisions from the view tab, sheet composition panel and selecting the sheets issues/ revisions menu.
  • Click on the revision schedule in a title block to display a revision schedule on a sheet.
  • If your sheet view includes revision clouds, the revision schedule automatically displays information on revisions. 
  • You control these attributes of the revision schedule by modifying the title block family.
  • You can also got to the manage tab - click on additional settings and in the drop down select sheet issues/ revisions to view the same.

revisions.png

Let us know if you have additional questions.

Please mark this response as "Accept as Solution" if it answers your question to help others seeking similar solutions. Kudos gladly accepted.

Message 10 of 13

ToanDN
Consultant
Consultant
Accepted solution

@Anonymous

 

Below is an example to limit the number of Revisions in the schedule.

 

Capture.PNGCapture1.PNGCapture3.PNG

Message 11 of 13

Anonymous
Not applicable

@Viveka_CD Thanks for the explanation. That was really helpful.

 

Message 12 of 13

Anonymous
Not applicable

Great!!! Thank you for the help. 🙂

Message 13 of 13

Viveka_CD
Alumni
Alumni
Accepted solution

Hi @Anonymous

I glad to hear that you found this helpful!

Please feel free to reach out if you have any questions.