Hi all, I created a door schedule and I only want to show the doors in the phase "new construction". while I set the schedule for the "New Constriction" but it shows all doors. 

 

Can someone help me?

Accepted solutions (1)
1,269 Views
1 Reply
Reply (1)
Message 2 of 2

ToanDN
Consultant
Consultant
Accepted solution
The phase filter of the schedule should be Show New Only.