Hi all, I created a door schedule and I only want to show the doors in the phase "new construction". while I set the schedule for the "New Constriction" but it shows all doors. 

 

Can someone help me?

 

Capture.PNG

0 Likes
Accepted solutions (1)
609 Views
1 Reply
Reply (1)
Message 2 of 2

syman2000
Mentor
Mentor
Accepted solution

When you create the schedule, you have to modify the phase filter from Show complete to Show new.

 