Hi, I need to generate an excavation at different stages in Revit. I need to go climbing first at a depth of 3m and then go down to 7m. 
I try to do it with building pad but it can't overlap. I would like to know ¿How  can I do it?
Thanks
0 Likes
Accepted solutions (1)
987 Views
3 Replies
Replies (3)
Message 2 of 4

ToanDN
Consultant
Consultant
Accepted solution
The -3m pad should be created in phase 1, demolished in phase 2. The -7m pad should be created in phase 2. They should share the same sketch boundary.
Message 3 of 4

barthbradley
Consultant
Consultant

Can you elaborate? What do mean by "stages" , "climbing", "overlapping"? 

 

Illustrations might help. 

0 Likes
Message 4 of 4

agustinbarovero
Contributor
Contributor

The problem it was in the phase of demolished.