By testing propals of briges there is the following behaviour. It's more an idea than a defect. That's why I post it here.
I build a bridge and I made some modifications of the placement of one pier. After that I changed the type of the bridge from paramatic to steel. The pier is moving to the original place, that means the seetings I did are resetted. It would be better if the placement of the pier remains if the type of the bridge is changed. (see video)
Another beahviour:
- If you don't change the placement of the piers and only change the number of Piers (from 3 to 6), the piers are resetted to the original number after changing the type of the bridge.
- After changing the number of the piers again (from 6 to 3) the piers are again at the original place.