bridge components for split road merging into dual

Hello engineers, I modeled a 1.3km road in civil 3d and it splits from chainage 0 to 300m then the rest proceeds as a dual carriage way, for the split section, I used the assembly called lanefromtaperedmedian1 which ships with civil 3d, now when I import this road into infraworks, I was expecting infraworks to add individual piers and separate decks for the split section, and insted when I add bridge, I just see it adds one pier covering the split section from left to right, and even the deck is covering both splits and not individual splits, I needed the space between the splits to be an empty space with no deck or pier covering the space, is there away I can achieve this in Infraworks, or it will need me to model it as two roads in civil 3d, I have attached the civil 3d file and some infraworks screenshots, thanks a lot in advance

Tags (1)
1 REPLY 1
Message 2 of 2
hamzatariq70
in reply to: oliverkisera

This is one of the limitations in Infraworks currently. I would suggest you create two offset alignments and then make two separate corridors. In this way you will be able to create the separate bridges.