I am trying to perform nonlinear static analysis for my model. I am trying to get new stresses and displacement for my 100+m building.
Right now it has calculated for 24h and it seems that it does not want to stop.
Is there some way that i can still achieve the results with getting smaller accuracy or set other options to speed it up.
I have set the nonlinear part only for one combination,added the current status and options used.
I cannot figure out, interation number means that it will do maximum 40 of them in one calculation? and then if it is successful before 40, it moves up to the next increment?
By that logic if it does not fail, it will take a week?
Any wisdom or help is welcome