This project has multiple phases, potentially unique revisions within each phase, and unique dates corresponding to each phase. Everything else in the title blocks should remain the same across the project (project info, initials, etc.)
Is there a way to make updates to one title block without it affecting all the title blocks of all phases? I made copies for each phase and loaded them in individually, but when I updated the date on one, they all updated, even though they were separate families. I've missed something obvious, and preemptive thank you for any help/suggestions.
Solved! Go to Solution.
Solved by jay_colcombe. Go to Solution.
This could be due to the use of the Project Issue Date which is common to ALL Sheets.
You could alternative swap this for the sheet Issue Date (in Yellow) so it is singluar or create a New shared Parameter for Phase Issue Date?
Thank you! I changed the Tag Label in the family from Project Issue Date to Sheet Issue Date.