I created a new assembly and sheet, then created views and schedules for that sheet. The default schedules that show up in the Create Assembly Views doesn't contain a schedule for the Fabrication Parts->Plumbing Fixtures.

I am not sure how I did it, but I was able to get a schedule created for this sheet containing families from the Plumbing Fixtures catagory.

Now I am trying to create another assembly and sheet with the same schedule, but I cannot change the default schedules to show Plumbing Fixtures.

If you look at the Create Assembly View dialog for the first sheet, it shows a Plumbing Fixtures schedule available to select, but the Create Assembly View dialong for the second assembly sheet doesn't have it available?

Contains Plumbing Fixture ScheduleContains Plumbing Fixture ScheduleDoesnt Contain Plumbing Fixture ScheduleDoesnt Contain Plumbing Fixture Schedule

Can anyone assist with this?

Thank you!

0 Likes
258 Views
2 Replies
Replies (2)
Message 2 of 3

RobDraw
Mentor
Mentor

Do you have any plumbing fixtures in the assembly?


Rob

Drafting is a breeze and Revit doesn't always work the way you think it should.
0 Likes
Message 3 of 3

jwlewis777
Contributor
Contributor

Lol, no.
Thank you for the help.
Only Revit can make people do stupid things like this, lol.