This question has probably been asked many times before mine but I am unable to find the answer. Currently I am involved with designing the kitchen for restaurants, schools, hospitals etc... I perform the equipment layout with a Architecture template so I can also develop the elevations. Then I link that template to my systems template to be able to develop the MEP's. I just needed to know if this is the most efficient way of doing this or is there a better way? Thank you very much for your time and help.
Solved! Go to Solution.
Solved by hmunsell. Go to Solution.
Are you linking Templates (.RTE) or are you linking Project Models (.RVT) files?
if your linking Project Models then yes, that is the typical way for MEP and Arch to work. The work is done in there respective models and then linked together. Levels, Grids and some other items can be Copy Monitored as needed for coordination.
if your Linking Templates... I defer to @RobDraw.
Howard Munsell
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
Can't find what you're looking for? Ask the community or share your knowledge.