Yes / No project param in schedule

Yes / No project param in schedule

Anonymous
Not applicable
542 Views
2 Replies
Message 1 of 3

Yes / No project param in schedule

Anonymous
Not applicable

I took over a project where the issued sheets were being kept tract of using a Yes/No project parameter. Before it's Yes or No, it's blank. But once it's changes, it appears to have to be either Yes or No. Is there a way to reset the parameter to appear blank in the schedule?  Thanks.

 

Y-N-SCHEDULE.PNG

0 Likes
Accepted solutions (1)
543 Views
2 Replies
Replies (2)
Message 2 of 3

Alfredo_Medina
Mentor
Mentor
Accepted solution

No. The initial value of yes/no parameter is "null". Once you activated with Yes, it can't go back to "null". 


Alfredo Medina _________________________________________________________________ ______
Licensed Architect (Florida) | Freelance Instructor | Profile on Linkedin
0 Likes
Message 3 of 3

Anonymous
Not applicable

That's what I was afraid of. I switched them to Text parameters. Thanks.

0 Likes