Message 1 of 14
Not applicable
08-23-2018
10:37 PM
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
Hello!
Can anyone help me understand this? I practice in Colorado and my sites are always over 5000'. I do NOT understand how the toposurface tool is built in Revit. I just want a reliable way to do the following:
- Model a toposurface based on Navd 88 sea level elevations that I get from a surveyor.
- Display my first floor as 100'-0" in sections and elevations.
- Show true sea level elevations in a site plan.
- Only use one model. My brain is not that big.
My major gripe is this: Why can't a toposurface be based on survey point? If it could be, then you could make micro-adjustments to project basepoint to move your building up/down, and N,S,E,W based on site constraints. If a toposurface is based on project base point, you can't move the building without moving the toposurface, that seems like a major flaw. Am I missing something here?
Solved! Go to Solution.