Hello community,

We need to Split a schedule into two sheets, because is too long, there is no way we can sort it by any field because is the way it needs to be, any idea???

Many thanks!!!

0 Likes
1,827 Views
9 Replies
Replies (9)
Message 2 of 10

HermanSolomon
Advocate
Advocate

What you can try is to create a project parameter for the scheduled category, called Element Sheet No. This parameter should be an instance. Depending on the category, and how you are sorting and grouping these elements, you should be able to select all elements that needs to show on sheet 1 and add 1 to the Sheet No field. Add the Element Sheet No. parameter to the schedule, but hide the category in the formatting properties. You can then filter your schedule according to the Element Sheet No. that Equals, 1. The schedule can be duplicated and the filter condition changed to 2 for your second schedule. 

 

If you choose to use this method, I would advise to have a master schedule where the Element Sheet No field is visible and no filtering conidions have been set up. If any other element belonging to the category gets added to the project, you will be able to quickly add the Element Sheet No value to ensure the element is included in the schedules which are added to the sheets

http://revitrecess.blogspot.com/
0 Likes
Message 3 of 10

L.Maas
Mentor
Mentor

Depending on the situation you would have to resort to some creative solutions.

 

-Add a new parameter to the items in the schedule (e.g. Destination_Sheet). FIll the parameter with 'Sheet1' or 'Sheet2' and filter on this parameter

-Put  you Items in different phases and filter your schedule on those phases

-Create the schedule twice and put one on sheet 1 and the other on sheet 2. You can use  annotation to cover the parts wihich you do not need.

-Export your data to for example excel and reimport them as two images

-Use larger sheet

-....

 

You can possbily think of several more different creative solutions. It depends on your project and schedule to find the most appropriate solution

 

 

Louis

EESignature

Please mention Revit version, especially when uploading Revit files.

0 Likes
Message 4 of 10

Anonymous
Not applicable

Thank you very much guys!!!

0 Likes
Message 5 of 10

Anonymous
Not applicable

We are using the Archigrafix Reports. This tool automatically splits long schedules into a PDF document with multiple pages. It also exports to Word or sends to a printer. You can have a look on the link on Archigrafix Reports. What we like it that once all the settings for a schedule are set it automatically saves them. We export drawing lists about 50-100 times per project, so this tool really helps us save time.

 

dialog_preview_create_1

 

 

 

 

Message 6 of 10

ToanDN
Consultant
Consultant
I think they were talking about split a long schedule on multiple Drawing Sheets in Revit.
0 Likes
Message 7 of 10

Anonymous
Not applicable

I have used the filter technique previously; I think the right approach in a production environment is an automatic process that allows the schedule data (nr. of rows) to expand and contract. For instance: the schedule may need to spread into another page as it does not fit on the last page. Therefore I believe that a tool like archigrafix reports is more convenient, faster and professional then the manual process of setting filters and split into revit sheets. 

0 Likes
Message 8 of 10

ToanDN
Consultant
Consultant

I agree with what you think. But the tool you mentioned does not actually address a solution to have the schedule tables on Sheets in the construction document. Create reports as separate documents can be done right off the bat.  Export it to Excel and make multi-page PDF from Excel take a few mouse clicks.

0 Likes
Message 9 of 10

Anonymous
Not applicable

Hi spitffire-s

 

Thank you. I'll give it a try to the archigrafix reports. This is what I've been looking for a long time.

0 Likes
Message 10 of 10

bms953
Advocate
Advocate

it's possible, take a look to this page:  https://dddmodeling.wordpress.com/2016/10/06/useful-tricks-break-schedules-per-sheet-in-revit/

 

Behzad Meskini

Competitor in World skills Competition 2005 Finland (Mech,Eng,CADD)
Member of Iranian Elite Foundation
Autodesk Certified Professional-AutoCAD
Autodesk Certified Professional-Inventor Pro
Autodesk Certified Professional-3ds Max
Autodesk Certified Professional-Revit Architecture
Autodesk Certified Professional-Revit Structure
Autodesk Certified Professional-Revit MEP
DS CATIA Certified V5 Mechanical Surface Designer Specialist
DS CATIA Certified V5 Associate - Part Design
DS CATIA Certified V5 Associate - Surface Design
DS Solidworks-CSWP-Mechanical Design Professional
DS Solidworks-CSWA-Advanced Sheet Metal Professional
DS Solidworks-CSWA-Advanced Weldments Professional
DS Solidworks-CSWA-Advanced Surface Professional
DS Solidworks-CSWA-Advanced Drawing Professional

0 Likes