I have been wresteling with this problem for some time. I do alot of smaller projects. Most of the time a survey with countours does not exist. So I go out to the site with a laser level, take grades, and create a site model with that information using the first floor level as base datum 100 feet or sometimes 0.
Then later on mabey I'll find a good benchmark and then have to adjust everything to the new elevation data. Pinning, unpinning the project basepoint, moving everything up and down and so forth. It's a real hassel and I have yet to figure out the real reason why some thing are acting the way they do. It's alot of trial and error, and when it gets right, I don't know how I got there.
Please see the attached project file. It's from Revit 2017 but I've experienced the same problems from 2014 on. Go to edit the sites and observe the elevations of the points used to create the sites. They seem to have no relation to the survey point or project base point.
What's up? The only narritave that makes sence to me is that there is an invisiable set of coordinates that got thrown off with all of my manuvering.
Thanks,
Rudy Beuc
I have been wresteling with this problem for some time. I do alot of smaller projects. Most of the time a survey with countours does not exist. So I go out to the site with a laser level, take grades, and create a site model with that information using the first floor level as base datum 100 feet or sometimes 0.
Then later on mabey I'll find a good benchmark and then have to adjust everything to the new elevation data. Pinning, unpinning the project basepoint, moving everything up and down and so forth. It's a real hassel and I have yet to figure out the real reason why some thing are acting the way they do. It's alot of trial and error, and when it gets right, I don't know how I got there.
Please see the attached project file. It's from Revit 2017 but I've experienced the same problems from 2014 on. Go to edit the sites and observe the elevations of the points used to create the sites. They seem to have no relation to the survey point or project base point.
What's up? The only narritave that makes sence to me is that there is an invisiable set of coordinates that got thrown off with all of my manuvering.
Thanks,
Rudy Beuc
Hi Rudy!
Unfortunately, you are right. Topography doesn't have any relation to the survey or project base point (at least I was not be able to find one).
What's going on is next: when you create the topography, it's "zero" is at project base point (relative project zero).
But, if you change your Project Base Point (PBP), (you change project relative zero), your topo will stay where it is.
Then, you move it, for example 100m up to stay right where it should be in reality, when you edit it, points of the topography will still have "0" and all of the original point elevation values.
What I usually do is to create topography based on the AutoCAD dwg lines or points on the "correct" altitudes.
Hope it helps!
Hi Rudy!
Unfortunately, you are right. Topography doesn't have any relation to the survey or project base point (at least I was not be able to find one).
What's going on is next: when you create the topography, it's "zero" is at project base point (relative project zero).
But, if you change your Project Base Point (PBP), (you change project relative zero), your topo will stay where it is.
Then, you move it, for example 100m up to stay right where it should be in reality, when you edit it, points of the topography will still have "0" and all of the original point elevation values.
What I usually do is to create topography based on the AutoCAD dwg lines or points on the "correct" altitudes.
Hope it helps!
This video might help. it shows how to set up a project to place toposurface elevation points using sea level elevations.
http://help.autodesk.com/view/RVT/2017/ENU/?guid=GUID-B73E0D49-3330-4876-B8BD-7C23B9340626
This video might help. it shows how to set up a project to place toposurface elevation points using sea level elevations.
http://help.autodesk.com/view/RVT/2017/ENU/?guid=GUID-B73E0D49-3330-4876-B8BD-7C23B9340626
Ok, so by that reasoning, if I create a new site massing with points at absolute elevation 0, then the sithe should be in line with the project base point.
Please see the attached file "Project1-A". It did not seem to work out that way.
Thanks,
Rudy Beuc
Ok, so by that reasoning, if I create a new site massing with points at absolute elevation 0, then the sithe should be in line with the project base point.
Please see the attached file "Project1-A". It did not seem to work out that way.
Thanks,
Rudy Beuc
Ok, have never used the relocate project tool to change elevtions. Have been moveing the project and survey base points.
Why isn't just moving the survey point have the same effect?
Thanks,
Rudy Beuc
Ok, have never used the relocate project tool to change elevtions. Have been moveing the project and survey base points.
Why isn't just moving the survey point have the same effect?
Thanks,
Rudy Beuc
Hi, I wrote from head so I probably wrote it wrong.
Here, http://screencast.com/t/cfdPFj0sgar7
I recorded a short video to show you what I was trying to say.
As you can se, movin WILL change topo points height, but changing the UNCLIPPED Project Base Point and/or Survery point will not change the topo points heights.
Hi, I wrote from head so I probably wrote it wrong.
Here, http://screencast.com/t/cfdPFj0sgar7
I recorded a short video to show you what I was trying to say.
As you can se, movin WILL change topo points height, but changing the UNCLIPPED Project Base Point and/or Survery point will not change the topo points heights.
Moving the Survey Point CLIPPED has the same effect...it would mean basically; indirectly relocating/moving your whole project (including the Revit Plate ie: Start-up Origin together with the Project Base Point) to a point E:??/N:?? from the origin of the WCS 0,0,0. When it is clipped it means it is clipped to the World Coordinates system. and at start-up (new project template) both WCS and Revit Coordinates System are at 0,0,0
(The benchmark/Survey Point) At this instance - after relocating it clipped
That point identifies where your site is with respect to the E0,N0
What you need to watch out for is the project base point ... moving it un-clipped is what causes the mess. And for that reason; using a master file for the site separate from that of the building especially when you have more than 1 building on the plot. ie: you use shared coordinates ...which comes best into play when you start modeling your project before you receive any survey data.
Project Base Point
When the Project base point is clipped it means that it is clipped to the Revit Plate where you are modeling and start-up origin. When you un-clip it and move it around it implies moving it away from the start-up origin. On small projects this has less significance BUT on large scale projects where the site and/or the elements/buildings on it exceeds 9.9 miles radius/distance between their extent; there is a chance that the project (entirely of partially) falls outside the 20 miles radius from the start-up origin (that's when Revit will prompt you)
Un-clipping the base point and moving it is more like telling the builder - instead of measuring from the Finish floor level, measure from 1m above finish floor level...or instead from this corner of the building, from the other/opposite corner. I personally never found a reason to move it un-clipped further than those extents (1-20m from where it originally was - the start-up origin) and that is another reason why not to un-clip it through out the whole project till you are set to fine tune the spot coordinates placed in the project.
Changing the elevation
This is the least critical...it can be as easy as
Some leave the Survey point as is for some odd reason; but I find that ridiculous. Project at 2000 m from sea level and benchmark at sea level!!!... elevation has to go in both otherwise the benchmark doesn't make sense
The other way to this is
The only way to understand this is to really understand the 2 coordinates systems .. That of Revit/Project and the WCS (ie: on the 3D view that would be respectively the Cube which resembles the project & project north and the circular compass which resembles the WCS & True North)
Sorry I cannot open your file I don't have 2017
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
Moving the Survey Point CLIPPED has the same effect...it would mean basically; indirectly relocating/moving your whole project (including the Revit Plate ie: Start-up Origin together with the Project Base Point) to a point E:??/N:?? from the origin of the WCS 0,0,0. When it is clipped it means it is clipped to the World Coordinates system. and at start-up (new project template) both WCS and Revit Coordinates System are at 0,0,0
(The benchmark/Survey Point) At this instance - after relocating it clipped
That point identifies where your site is with respect to the E0,N0
What you need to watch out for is the project base point ... moving it un-clipped is what causes the mess. And for that reason; using a master file for the site separate from that of the building especially when you have more than 1 building on the plot. ie: you use shared coordinates ...which comes best into play when you start modeling your project before you receive any survey data.
Project Base Point
When the Project base point is clipped it means that it is clipped to the Revit Plate where you are modeling and start-up origin. When you un-clip it and move it around it implies moving it away from the start-up origin. On small projects this has less significance BUT on large scale projects where the site and/or the elements/buildings on it exceeds 9.9 miles radius/distance between their extent; there is a chance that the project (entirely of partially) falls outside the 20 miles radius from the start-up origin (that's when Revit will prompt you)
Un-clipping the base point and moving it is more like telling the builder - instead of measuring from the Finish floor level, measure from 1m above finish floor level...or instead from this corner of the building, from the other/opposite corner. I personally never found a reason to move it un-clipped further than those extents (1-20m from where it originally was - the start-up origin) and that is another reason why not to un-clip it through out the whole project till you are set to fine tune the spot coordinates placed in the project.
Changing the elevation
This is the least critical...it can be as easy as
Some leave the Survey point as is for some odd reason; but I find that ridiculous. Project at 2000 m from sea level and benchmark at sea level!!!... elevation has to go in both otherwise the benchmark doesn't make sense
The other way to this is
The only way to understand this is to really understand the 2 coordinates systems .. That of Revit/Project and the WCS (ie: on the 3D view that would be respectively the Cube which resembles the project & project north and the circular compass which resembles the WCS & True North)
Sorry I cannot open your file I don't have 2017
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
Thanks everyone for thier posts. The discussion was good.
Right now, so far as I can figures, the points used to create the site massing are using the hidden internal set of coordinates; not the project base point or survey base point grids.
I think unclipping the project base point and moving thing around like I did in earlier projects caused the project base p[oint to be disconnected form the hidden internal set of coordinates, or wcs as RDAOU calls it. Understanding this is important because I have to fix my project template file.
I think I've figured this out, please see the attached file.
Thanks agian,
Rudy Beuc
Thanks everyone for thier posts. The discussion was good.
Right now, so far as I can figures, the points used to create the site massing are using the hidden internal set of coordinates; not the project base point or survey base point grids.
I think unclipping the project base point and moving thing around like I did in earlier projects caused the project base p[oint to be disconnected form the hidden internal set of coordinates, or wcs as RDAOU calls it. Understanding this is important because I have to fix my project template file.
I think I've figured this out, please see the attached file.
Thanks agian,
Rudy Beuc
Hey all ...
continued digging and found a great AU course...
Still think the points used for generating a site massing are tied to the invisable "double secrete" WCS.
Thanks,
Rudy Beuc
Hey all ...
continued digging and found a great AU course...
Still think the points used for generating a site massing are tied to the invisable "double secrete" WCS.
Thanks,
Rudy Beuc
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
@loboarch wrote:
There is an "origin" internal to Revit and it is not marked in any way. By default the Project Base Point starts at this position, but if moved un-clipped, the Project Basepont become separated from the "origin". You can set it back, by un-clipping the Project Basepoint and right clicking and select "Move to Startup Location".
There is an origin and ONE (ie: the user) can mark it because as long as the Project base point is clipped that origin moves along with the Project base point.
Use Relative spot coordinate and check it...I will record a screencast and upload it on from my side too
Difference with between relocating the project using Project base point and using the tool Relocate Project is that the latter ignores the status of the clip and moves the plate along anyways
EDIT: SCREENCAST - TRACKING REVIT PLATE / INTERNAL ORIGIN
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
@loboarch wrote:
There is an "origin" internal to Revit and it is not marked in any way. By default the Project Base Point starts at this position, but if moved un-clipped, the Project Basepont become separated from the "origin". You can set it back, by un-clipping the Project Basepoint and right clicking and select "Move to Startup Location".
There is an origin and ONE (ie: the user) can mark it because as long as the Project base point is clipped that origin moves along with the Project base point.
Use Relative spot coordinate and check it...I will record a screencast and upload it on from my side too
Difference with between relocating the project using Project base point and using the tool Relocate Project is that the latter ignores the status of the clip and moves the plate along anyways
EDIT: SCREENCAST - TRACKING REVIT PLATE / INTERNAL ORIGIN
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
Perhaps I haven't been too clear.
I think we're in agreement more than it seams.
Figuring this out has been a long term process. About two years. Over that time I've been updating my inhouse project template file, and apparently have introduced a mistake. I believe that when wrestling with the elevation of points making up a site massing; that is clipping , unclipping the project base point, and moving things around; caused the project base point to become disconnected from the internal WCS of the file. This problem got embedded in my project template file and has existed in every project since then.
Please see the attaches screenshot. The elevation of the point used to create the site has no relationship to the project base point or survey point. I believe the 0 refrences the files internal and hidden coordinate system (or what we are now refreing to as the WCS).
My confusion in the past was not realizing there was a hidden internal coordinate system. I thought the survey point represented one system and the project base point represented another. Then in the process of working with sites, I found thses points sitting on an elevation of 0, but 0 in relation to what?
Figuring this out shoulldn't have been this hard. From here on out I will be graphically marking that 0,0,0, refrence point (WCS) in my flies. What'll be the most appropriate way of doing that I have yet to figure out. Perhaps a set of pinned work planes.
Thanks,
Rudy Beuc
Perhaps I haven't been too clear.
I think we're in agreement more than it seams.
Figuring this out has been a long term process. About two years. Over that time I've been updating my inhouse project template file, and apparently have introduced a mistake. I believe that when wrestling with the elevation of points making up a site massing; that is clipping , unclipping the project base point, and moving things around; caused the project base point to become disconnected from the internal WCS of the file. This problem got embedded in my project template file and has existed in every project since then.
Please see the attaches screenshot. The elevation of the point used to create the site has no relationship to the project base point or survey point. I believe the 0 refrences the files internal and hidden coordinate system (or what we are now refreing to as the WCS).
My confusion in the past was not realizing there was a hidden internal coordinate system. I thought the survey point represented one system and the project base point represented another. Then in the process of working with sites, I found thses points sitting on an elevation of 0, but 0 in relation to what?
Figuring this out shoulldn't have been this hard. From here on out I will be graphically marking that 0,0,0, refrence point (WCS) in my flies. What'll be the most appropriate way of doing that I have yet to figure out. Perhaps a set of pinned work planes.
Thanks,
Rudy Beuc
Best Practice is to mark both
1. the WCS 0,0,0 (ie: at sea level)
2. the Center of the Revit plate (ie: start up point) --- As shown in the above screentcast
Then you should be able to track both systems (WCS and RCS) as you progress ... When you see the center of the plate markup didn't move along with the Project Base Point ... you will know that you did something wrong ie: you moved PBP unclipped
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
Best Practice is to mark both
1. the WCS 0,0,0 (ie: at sea level)
2. the Center of the Revit plate (ie: start up point) --- As shown in the above screentcast
Then you should be able to track both systems (WCS and RCS) as you progress ... When you see the center of the plate markup didn't move along with the Project Base Point ... you will know that you did something wrong ie: you moved PBP unclipped
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
Can't find what you're looking for? Ask the community or share your knowledge.