Room Calculation Point

Room Calculation Point

Anonymous
不适用
1,150 次查看
2 条回复
1 条消息(共 3 条)

Room Calculation Point

Anonymous
不适用

I have created a room placard family (attached) and it works 90% of the time (I have two families, placing it inside or outside of the room). I am using the room calculation to pull the room and level information. The error is arising when I insert it into my workstation family. I have 1440 workstations, but 341 of them aren't pulling any information. I have figured out the following:

 

  • project is 16 floors
  • floors 6 and 8 are an earlier bid pack (phase 1)
  • signage is all the same phase (phase 2)
  • all workstations on 6 and 8 aren't pulling room and level information (if i delete the workstations, i have no more unidentified floors/rooms)
  • i have tried changing the phase of the view, and the workstations--no change

 thanks.

0 个赞
已接受的解答 (1)
1,151 次查看
2 条回复
回复 (2)
2 条消息(共 3 条)

L.Maas
Mentor
Mentor
已接受的解答

Rooms are phase dependent. So if your rooms are phase 1 and signage phase 2 then it is correct that your signage will not see the room.

Create/Copy your rooms also in/to phase 2.

 

Louis

EESignature

Please mention Revit version, especially when uploading Revit files.

3 条消息(共 3 条)

Anonymous
不适用
that was it! i always forget about the room being phased...thanks so much!
0 个赞