Hi All,
I've got a number of schedules created and once I got the hang of how revit likes this its gone pretty good.
I've got a material take off schedule (see attachment) to which i've added a project parameter called Waste Factor. Now most of the time adding a value in this column works great. enter a value for the material its added to the # of units and life is good.... EXCEPT sometimes when you add a value in one Waste factor blank it adds it in a few other blanks... this doesnt work very good when different types of materials require different waste factors....
Anyone have any ideas why entering a value in one blank sometimes adds the same value to another spot? See attached images. In the 4th section under doors, i added 1.05 to the second waste factor blank under the Jambs material and it added the same value to the Gypsum Corner Bead and the Door stop materials.
This also happens if I add a value to the Gypsum Board - Standard 1/2" x 54" x 12' material under walls the same value is added to the "Paint - Dulux Diamond Matte" material...
Thanks in advance.