Panel Schedule BLANK - Transfer standards NOT WORKING

Panel Schedule BLANK - Transfer standards NOT WORKING

Xion_arq
Contributor Contributor
1,147 Views
13 Replies
Message 1 of 14

Panel Schedule BLANK - Transfer standards NOT WORKING

Xion_arq
Contributor
Contributor

Hello. 

Anytime I try to create  panel schedule is in BLANK. I've already created a new electrical project and transferred the standards (panel schedule: Branch panel) a hundred times, and still not working, the panel is still in BLANK. I even opened an old project of mine with panel schedules perfectly working, transferred the standards, and nothing.  I need help!

 

 

Xion_arq_0-1718985548415.png

 

0 Likes
1,148 Views
13 Replies
Replies (13)
Message 2 of 14

Tom_Kunsman
Collaborator
Collaborator

Do you have any loads applied to the panel?

If you find my post interesting, feel free to give a Kudo.
If it solves your problem, please click Accept to enhance the Forum.
0 Likes
Message 3 of 14

barthbradley
Consultant
Consultant
Message 4 of 14

Xion_arq
Contributor
Contributor
Yes, As I commented, I even transferred standards from previous projects were I created panels.
0 Likes
Message 5 of 14

Xion_arq
Contributor
Contributor
Yes.
0 Likes
Message 6 of 14

barthbradley
Consultant
Consultant

Did you choose a Template that you Transferred into Project? 

 

...if not, right-click on the Panel Schedule you created in the Project Browser and select "Change Template".  Then select the Template to apply. 

 

Change Template.png

Message 7 of 14

Xion_arq
Contributor
Contributor
Yup, still in Blank. I even re-installed Revit last night.
0 Likes
Message 8 of 14

barthbradley
Consultant
Consultant

Let's see your file. Post it here.  In fact, post both files: the one you're working on and the one you're transferring schedules from.  

0 Likes
Message 9 of 14

Xion_arq
Contributor
Contributor

Here you go. I hope you find something

Message 10 of 14

ToanDN
Consultant
Consultant

Transfer Project Standards from the Multi Discipline template and use the panel schedule template below:

 

ToanDN_0-1718992796738.png

 

0 Likes
Message 11 of 14

barthbradley
Consultant
Consultant

No issues here with either Project. 

 

Panel Sched1.pngPanel Sched2.png

 

 

REPORTING SOLE PANELBOARD IN A-2024-06-2531 EAGLE-JUNE-06.rvt:

 

Panel Sched3.png

Message 12 of 14

Xion_arq
Contributor
Contributor
Could it be my Revit? Or maybe view settings?
0 Likes
Message 13 of 14

barthbradley
Consultant
Consultant

@Xion_arq wrote:
Could it be my Revit?

 

I don't know how.  Are you OVERWRITTING when using TPS?  Maybe you're not. That might explain the problem.  

Message 14 of 14

yes_and_no
Collaborator
Collaborator

hnA_20240622_123622.jpg

0 Likes