Moving multiple views from one sheet to another, at once

Anonymous
Not applicable

I am organizing multiple callout views on a final sheet. I have a group that need to be moved to another sheet because there isn't enough room now. Instead of moving each view one by one, is there a way to move all of them simultaneously? I'm just wondering so it wont be very time consuming to move them one by one.

0 Likes
2,876 Views
6 Replies
Replies (6)
Message 2 of 7

barthbradley
Consultant
Consultant

you can drag and drop views from and to different sheets in the Project Browser, but doing multiples at a time and keeping their placement the same on the different sheet cannot be done using this method -- or any that I know of. 

0 Likes
Message 3 of 7

chrisplyler
Mentor
Mentor

If you want to move ALL the views from one sheet to another...just change the sheet number/name instead.

0 Likes
Message 4 of 7

ToanDN
Consultant
Consultant

@chrisplyler wrote:

If you want to move ALL more than half of the total the views from one sheet to another...just change the sheet number/name instead.  


FIFY

0 Likes
Message 5 of 7

chrisplyler
Mentor
Mentor

Sorry. I mean that if you don't want to individually move any, but if instead your purpose is to move everything from one sheet to another, for example because you forgot a sheet that should come ahead and now you want to insert it...you can instead just renumber the existing sheet to a later number and then create your new sheet with the earlier number.

 

0 Likes
Message 6 of 7

ToanDN
Consultant
Consultant

@chrisplyler

 

I know what you meant and we are on the same boat.  What I was trying to say is If I have 20 views on a sheet and 11 of them need to move to another one, I would renumber the original sheet and move 9 to a new sheet instead.

0 Likes
Message 7 of 7

chrisplyler
Mentor
Mentor

Yeah that would be the most efficient process.