Hi all

 

I cannot seem to join this gutter up

the fascia is an existing house roof fascia and already mitred and was fine - I have to demolish one gutter and replace a new gutter on the drawings - so thats easy enough, but in placing the new gutter I cannot get it to mitre up - join tools and trim tools do not work on gutters

 

all the usual factors are considered and no the issue:

- fascias are lined up yes

- horizontal and vertical positions are not changed

- its an existing fascia and it was perfect before with a properly mitred gutter so none of this should matter

 

also Southern Hemisphere here we spell it Mitre so not sure if that's different in the North - Miter??

 

Cheers

 

Darren

darren_0-1642118988454.png

 

 

0 Likes
782 Views
7 Replies
Replies (7)
Message 2 of 8

barthbradley
Consultant
Consultant

Yeah. Someone else that knows how to spell Mitre.  We're a dying breed, buddy.  

 

Post your file. 

 

...did you try slowly dragging the blue grip while holding your breath method yet?

0 Likes
Message 3 of 8

barthbradley
Consultant
Consultant

Check to see that the horizontal and vertical profile offsets match for both. 

0 Likes
Message 4 of 8

ToanDN
Consultant
Consultant

You cannot miter gutter segments under different phases.  There are some workarounds:

- Add a small return segment to gutter to be demolished.  Create new gutter with the same return and join new + existing.

ToanDN_0-1642126381314.png

- If you insist to demolish at the miter joint, add a small return segment to the new gutter and use a void to cut it at the miter joint.

 

ToanDN_1-1642126474683.png

ToanDN_2-1642126608896.png

ToanDN_3-1642126739159.png

 

ToanDN_4-1642126783764.png

 

0 Likes
Message 5 of 8

barthbradley
Consultant
Consultant

@ToanDN wrote:

You cannot miter gutter segments under different phases.  

 


 

I can.  

 

...assuming that is what the OP is trying to do.  I didn't understand it that way.  But whatever.  He should be able to "phase" the miter (a.k.a. mitre).

 

Mitre 1.pngMitre 2.png

Mitre 3.pngMitre 4.png

0 Likes
Message 6 of 8

wisedrawing
Collaborator
Collaborator

Classic

 

I thought something was up when 0 search returns came up for Mitre

 

pretty sure I got all the matchings correct - 

 

this probably brings up the point - an I force a mitre? regardless of matching etc. just make one?

 

cheers

 

 

attached file

0 Likes
Message 7 of 8

wisedrawing
Collaborator
Collaborator

Thanks for the work arounds ToanDN

 

see if we get to the bottom of it or not and I can use these in the mean time

 

cheers

 

 

0 Likes
Message 8 of 8

barthbradley
Consultant
Consultant

I can't open your file right now, but use this workflow:

 

  • Create a Mitered 2 Gutter condition by creating each Gutter separately (e.g. not in the same session).
  • Clipboard Copy/Paste Aligned to Same Place the Mitered 2 Gutters
  • Change the Phase Created/ Phase Demolished for each Segment. Example: Gutter 1a = Existing/None, Gutter 1b = Existing/New Construction, Gutter 2a & 2b = New Construction/None.
  • Change View Phase Filter/Phase to Show Complete/New Construction
  • Use Add/Remove Segment tool to select eave @ 1a.

 

 

 