(Kind of goes along with my last few posts for those that had been following...)
Let's say you want to demo the finish off of any existing wall and add a new finish.
Would you need to model the wall structure and put on existing phase, then model existing finish and put on demo phase, then model new finish and put on new construction phase?
Solved! Go to Solution.
Solved by barthbradley. Go to Solution.
Solved by hmunsell. Go to Solution.
you cant... that is a case where you would need to draw a main wall (existing) and then a second wall (the finish), back to back. OR if your only refinishing it, unless the new finish is dramatically different thickness, just tag it with a note.
Howard Munsell
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
Ha.... i learned something today.... i didn't know you could do that with parts. Nice!
Howard Munsell
Did you find this post helpful? Feel free to Like this post.
Did your question get successfully answered? Then click on the ACCEPT SOLUTION button.
Can't find what you're looking for? Ask the community or share your knowledge.