How can I create a level schedule?

How can I create a level schedule?

svalen
Advocate Advocate
1,267 Views
6 Replies
Message 1 of 7

How can I create a level schedule?

svalen
Advocate
Advocate

I'd like to create a level schedule, so that I have a place I can easily manage/edit my level (besides in elevations)

 

How can I do this? I'm not seeing a category for levels when creating a schedule? 

0 Likes
1,268 Views
6 Replies
Replies (6)
Message 2 of 7

ToanDN
Consultant
Consultant

Of course.  Choose Schedule/Quantities from View 

 

0 Likes
Message 3 of 7

barthbradley
Consultant
Consultant

Manage and edit them how? 

0 Likes
Message 4 of 7

svalen
Advocate
Advocate

I'd like to be able to delete levels that I do not need anymore.

I'd also like to be able to manipulate the heights of levels from a schedule.

 

Sometimes it is difficult to to edit levels in elevation because there are multiple 

levels very close to one another with tags overlapping,

or irrelevant levels that were a hold over from another project (I do a save as sometimes)

 

It just seems like it would be easier to manage levels from a schedule sometimes.

0 Likes
Message 5 of 7

barthbradley
Consultant
Consultant

@svalen wrote:

I'd like to be able to delete levels that I do not need anymore.

I'd also like to be able to manipulate the heights of levels from a schedule.

 

Sometimes it is difficult to to edit levels in elevation because there are multiple 

levels very close to one another with tags overlapping,

or irrelevant levels that were a hold over from another project (I do a save as sometimes)

 

It just seems like it would be easier to manage levels from a schedule sometimes.


 

 

Seems scary too me.  Maybe I'm just a worry-wart.  😉

Message 6 of 7

svalen
Advocate
Advocate

When I select levels this is all I get,  

svalen_0-1611714038978.png

 

Are you able to get all of the levels in your project listed?

 

0 Likes
Message 7 of 7

ToanDN
Consultant
Consultant
You need to add more fields to the schedule.