Hello,

 

I have a question: i have 2 schedules, one with Area areas and one with Room areas. Is it possible to calculate the percentage of these two areas?Area-Room calculation.jpg

0 Likes
1,227 Views
5 Replies
Replies (5)
Message 2 of 6

ToanDN
Consultant
Consultant
No. But you can create a new Parameter and add it as a field to the Room schedule, manually enter the Area value, then create a calculated value to get the percentage for each room.
0 Likes
Message 3 of 6

hve-architecten
Advocate
Advocate

Thanks!

 

Created a new project parameter (Area_verblijfsgebied) but now i cant calculate the percentage of 1 column to the other:

I just want for instance calculated that 88,9 / 160,7 * 100 = 55,3% !  I just cant get the formula right! 

Clipboard01.jpg

0 Likes
Message 4 of 6

Sahay_R
Mentor
Mentor

.....and Revit give you the 'inconsistent units' message, right?

 

Here's what you do - divide all the areas by 1.

 

Area/1.

 

That's it. This will make the units consistent.


Rina Sahay
Autodesk Expert Elite
Revit Architecture Certified Professional

If you find my post interesting, feel free to give a Kudo.
If it solves your problem, please click Accept to enhance the Forum.
0 Likes
Message 5 of 6

hve-architecten
Advocate
Advocate

Strange things happen in Revit:

 

Tried the following formula: (Area_verblijfsgebied / 1) / (Area / 1) and the result is this:

 

Clipboard01.jpg1,1 is just incorrect, needs to be 0,553. And some fields are empty?

0 Likes
Message 6 of 6

ToanDN
Consultant
Consultant

Do you have combined rows?  Check [Itemize every instance] under Grouping.  

 

 Capture.PNG5Josephine-TdN-624477.png

0 Likes