Why isn't "phase" there?
Gelöst! Gehe zur Lösung
Gelöst von RDAOU. Gehe zur Lösung
Are you using Revit 2022? Previous version don't have phase as schedule field.
Phase filter in schedule only exist in Revit 2022. Previous version don't have this.
Majority of the users would add-in shared parameter or project parameter and manually enter in those values.
What are you talking about here? Applying a Phase to a Schedule? That capability exists pre-2022.
Yes i mean, i want to find it on "fields"
Your schedule properties shows "phase created". mine isn't.
What could be the problem?
What do you mean by "whats the category"? the listed elements are all "Specialty equipment" if that's what you mean.
I've upgraded the project to 2022 and i still can't find "Phase created" field.
Maybe you Can't find them under available Fields because they have been already added to the schedule and/or added and set to hidden...
PS: No need for 2022 ... Phase Created and Phase Demolished fields are available fields in Spc.Equip schedules since long time back
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
Then it is most probably one of the following
You cannot change/switch the type of schedule once created...If it is only Specialty Equipment what you need, you have to re-create the schedule and use Specialty Equipment instead of Multi-Category
YOUTUBE | BIM | COMPUTATIONAL DESIGN | PARAMETRIC DESIGN | GENERATIVE DESIGN | VISUAL PROGRAMMING
If you find this reply helpful kindly hit the LIKE BUTTON and if applicable please ACCEPT AS SOLUTION
i re created the schedule as a specialty equipment sechdule. now it works. thanks all!
Sie finden nicht, was Sie suchen? Fragen Sie die Community oder teilen Sie Ihr Wissen mit anderen.