I'm typically a detailer and trying to come to terms with an approach to using REVIT that works with my details.
Let me first off say that I understand that I absolutely do not want to over detail in the model, But I see no reason why I can't at least consider "building" the walls and floors in a manner that is reasonably consistent with the way things are built. I've been doing quite a bit of cad modeling of revit files converted to dwg and I'm having to do a lot of work that in my mind is not necessary.
So, interested in getting some opinions if I'm being foolish or going to kill myself trying to do something similar to what I'm currently working on.
1. I want to get all my datums/ levels more or less ironed out prior to putting in floors and walls.
2. Have wall types with finishes that are unlocked at the bottom.
3. Have (relatively speaking ) a lot of levels with associated views (most will never make it to sheets) that are the building blocks of referencing the wall heights.
4. Levels currently as follows. Bottom of Footing. Top of Footing. Top of Slab. Top of foundation Masonry. Top of Foundation Plate. Top of main level subfloor. Top of main level plate. Top of upper level subfloor. Top of upper level plate. Top of attic joist. Top of attic plate. Roof.
5. Idea is as follows:
- I draw the footing with top and bottom constraints being top and bottom of footing.
- cmu foundation wall (say with stucco veneer) is drawn with constraints from top of footing to top of foundation masonry levels.
- Need a plate so draw a 5-1/2" wide by 1-1/2" tall wall set relative to the top of the cmu wall as required with top of masonry wall and top of plate as restraints
- Main level walls sit directly on top of the subfloor (modeled with the floor type).... but no finish floor with top of subfloor and top of plate (on top of cmu) as restraints.
- Main level walls have bottom exterior finish and sheathing unlocked so can pull down over rim joist and beyond as required.
- Upper level walls basically the same.
- Once everything modeled come back in and draw actual thickness floor finishes in the "rooms" on top of the subfloor.
As best I can tell this will work without being too cumbersome. Should be able to move levels and have everything move along with it, but I do understand that the plate on top of the cmu foundation wall and the height of the footings are going to need to be dealt with when changes are made.
I'll start with this.
Thanks in advance for any help.