Change contour options processing order

When we go in Results - Options, contour options, and specify the min/max, we know that the contours will change in the model. There is a wait time after checking the option that should not be there. Let us click the option, change the values and then, after pressing OK do the processing. 

1 Comment
John_Holtz
Autodesk Support

Hi @rpaquinUE26U .

 

This can be done with the current software. "System > Default Settings > Post-Processing" and uncheck the box "Automatic plot updating". After you make all the changes you want, click the "Display" button to update the contour. No need to wait X seconds waiting for the contour to update for each change you make. 🙂

 

John

 