Schedule & Primavera P6 - Physical % Complete

Schedule & Primavera P6 - Physical % Complete

We do our scheduling program in P6 and then upload it into ACC Schedule once a week but the "% complete" column does not correlate to "Physical % complete" and I already know it only translates "Duration % complete" correctly. The reason why we are and want to use the Physical option is we can write the percentage manually, but the Duration option is a fixed formula with respect to current date, start date and finish date.
My feature request is: Is it possible to add the usage of "Physical % complete" in ACC Schedule? so that it correlates correctly into "% complete"?

7 Comments
kevin_scottMTSYW
Community Visitor

Can a column be addednto ACC that indicates the actual physical % complete in ACC

Dyrmundur_Helgi
Contributor

That would be great @kevin_scottMTSYW but I don't think it is possible as is... maybe it is possible as a additional field within a activity. Not sure how that would work though.

Essential feature. Please priorise. Kind of show stopper today.

mohit_jainXER6C
Community Visitor

Have you found the solution, please let me know...

Dyrmundur_Helgi
Contributor
Hi, no I haven't got any response from Autodesk on this one. This bug is a huge problem for us still and I do not understand why this has not been addressed or fixed.
shai.friling
Autodesk

Hello @Dyrmundur_Helgi, Happy New Year,

Thank you for bringing this up.

We are aware of this feature enhancement request, and it is one of our top priorities for Schedules in Build.

It is expected to be worked on in the short term (the next few months).

I hope you are finding our product valuable, and would appreciate any additional feedback.

 

Best regards.

Dyrmundur_Helgi
Contributor

Hi @shai.friling, any updates on this? Our percentages are still wrong. Getting this right is very important to us.

 

Additional feedback: the Schedule tool does not load for many people within the company unless they go incognito. This is not good as we are presenting the Schedule as a tool/viewer in-house and also for our clients and subcontractors and most other externals.