I have a pipeline alignment that was extended, adding about 22 sheets to the plans. Because it was so long, I extended it by taking the existing alignment to the end of the last existing sheet, then starting a new alignment from that spot (so my new alignment starts at station 252+00), with the new alignment starting at sheet 22.
I have created viewframes and cut sheets for the new alignment. I thought I had everything correct- the sheet numbering is right, the tabs are labeled right, the matchline numbers are right in the matchline group. And yet when I actually cut my sheets, it started my match line labels at 1.
So now my match lines are all wrong. I can re-create the view frames if necessary since the sheets are all cut already, but how do I fix this? I thought when you set up the match line name while creating viewframes, it would control this but apparently not.
Solved! Go to Solution.