Hi,

My Client requires a custom template for daily logs, as the existing daily logs is not helpful for us in India for a construction site.

Our Daily Logs AKA (Daily Progress Report-DPR) consists of:

1. Contractor/ Agency Name:

2. Climate

3. Day

4. Date

5. DPR No. (For Tracking)
6. Today/s Manpower (Engineer, Safety officer, Project Manager, Welder, Plumber, Painter, Tile Mason, Carpenter, Electrician, JCB/ Poclain Operator, Driver etc)

7. Today's Work Done (Planned- inclusive of Planned quantity- Executed Quantity Left over etc, Time)

8. Tomorrow's Planning (same as above)

9. Hinderances with Number for Tracking

10. Delay's with Number for Tracking

11. Prepared By

12. Others