Hi there,
Date format mismatch in the 'Revision table' and 'Title block' on the drawing.
Token used in Title block is ‘DATE_ORDER’ – date in Project data is correct.
I would much appreciate the assistance in sorting this one out. Thank you in advance.
Regards,
Egis
Solved! Go to Solution.
Solved by ArjunGaba. Go to Solution.
@e.kajackas As you have selected date format regional so it is linked with you desktop date format settings . Their is two options two achieve one is two change desktop date and time settings as you want and another is to choose another option instead of regional but from my point of view first one is Good to go
That is what I also thought, however after some testing, it turns out that the title block date token is linked to the country of the region, where is revision table picks up a short date of either country of the region. That is what was confusing for me at the beginning. Thanks for your efforts 😊