Schedule & Primavera P6 - Physical % Complete

Schedule & Primavera P6 - Physical % Complete

We do our scheduling program in P6 and then upload it into ACC Schedule once a week but the "% complete" column does not correlate to "Physical % complete" and I already know it only translates "Duration % complete" correctly. The reason why we are and want to use the Physical option is we can write the percentage manually, but the Duration option is a fixed formula with respect to current date, start date and finish date.
My feature request is: Is it possible to add the usage of "Physical % complete" in ACC Schedule? so that it correlates correctly into "% complete"?