Hi
I am having trouble both tagging and scheduling varying rebar sets.
it is fine when i use the number bars individually but when i try to use bars as whole with suffix
the bar suffix or varying lengths are not displayed on the schedule, just the mar mark and the constant bar dimensions (on one line only)
any ideas on how to fix this ??
Lloyd
Solved! Go to Solution.
Solved by ovidiu_paunescu. Go to Solution.
When you're numbering the bars as a whole, you need to add the rebar number suffix and sort by rebar number, then rebar number suffix.
This will list all the bars.
Another way to display the bars in a shorter format, especially if they vary linearly is to use the calculate minimum and maximum for the bar length or the segment lengths
To do this, sort by rebar number only and, from the formatting tab, change the bar length calculation to "Calculate minimum and maximum"