hi how do i align my pile to my pile cap such that my there is no protruding piles above the pile cap (as seen in the photo)?

Both my pile cap and piles are family objects.

 

Capture4.JPG

0 Likes
1,238 Views
3 Replies
Replies (3)
Message 2 of 4

KrisAribal
Advocate
Advocate

You can use the align tool. Align the face of the pile to the desired place and lock it.

0 Likes
Message 3 of 4

ennujozlagam
Mentor
Mentor

edit your pilecap family > create a reference plane and align to that reference plane and lock or make a dimension and lock?. thanks





Remember : without the difficult times in your LIFE, you wouldn't be who you are today. Be grateful for the good and the bad. ANGER doesn't solve anything. It builds nothing, but it can destroy everything...
Please mark this response as "Accept as Solution" if it answers your question. Kudos gladly accepted.
0 Likes
Message 4 of 4

blog6NN
Community Visitor
Community Visitor

Thanks for your post. The concrete strength on the cast-in-situ pile is not good, in order to ensure the concrete
The strength of the concrete, the elevation of the top of the cast-in-situ pile will generally exceed the design pile top
the elevation. After the perfusion is completed, wait a few days before removing the place that needs to be removed.
Dig out, this is called breaking the pile, it can also prevent the height of the upper layer of the pile from being different.
Comply with standards, such as common immersed pipes, drilled holes, punched cast-in-place piles, etc.
Etc., it is also convenient for people to check the place where the concrete is poured.