Phases from Linked in Model/Phase Mapping Best Practices
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
Start off by saying I'm new to using phases in a project. So, I have an electrical central model with arch new, arch exist and structural existing models linked in. A little confused how to phase this project. Should I create phases in my project that match one of the linked in models? Then map them together. Which models phasing should I follow to have all the models show up correctly on my views. Should I create my own phases (arbiritary naming) and map one of the linked in models phases to these phases? Will I incounter any issues with the phase filters not showing expected information being pulled from all the linked in models compared to my model? I guess this is multiple questions in one. Kind of lost a little. Any help would be great.
Thanks.