Does anybody have an elegant way to link space colorization (and hatching) to mechanical equipment?
I have perhaps 20 Terminal Units (mech eqpm) and perhaps 100 spaces. I'm trying to create a plan that is colorized where I can 'link' spaces to the Terminal Units, so that if a space is deleted the colorization goes away, or if a TU name/number changes, the colorization legeng changes as well.
Is it possible to create a Key Schedule for spaces where the list of keys is populated by the Terminal Units?
Right now I have it configured as a 2 step process where if a TU name is changed, a Space Key Schedule must also be separately changed. Any suggestions are appreciated.
Dustin
Trying to do a similar thing, but linking the zone to the terminal unit such that zoning schedules can automatically populate information from the unit. Any luck with what you're trying to do?
No, I was never able to link those things like I wanted to, sorry.
Can't find what you're looking for? Ask the community or share your knowledge.