Handling drainage/vent piping and view ranges
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
I'm trying to figure out what the most practical way to handle sanitary, storm, and vent piping in Revit. I want to improve my strategy to something more practical and I'm curious what other people do.
This is how I currently handle drainage plans; I have one single view for each level that shows all sanitary, storm, and vent piping. I slope all piping to make sure fall is coordinated with architecture and structure. For a multistory building, we show sanitary and vent piping serving fixtures on the first floor, on the first floor plan. So our view range is a couple feet below level up to a couple feet below the level above, so under slab sanitary is visible and we don't see second floor under slab sanitary piping on the first floor. For storm piping, we like to handle that as if the cut plans were floor to floor.
Assuming the above makes sense to anybody other than just me, this presents a few problems:
- Depending on how the architects setup their model, it can sometimes be difficult to show walls correctly. For instance, sometimes it's difficult to not see the walls on the floor below due to the cut plan being below the floor. Usually it's possible to override the architect's model with a view from their model, but that's not always the case.
- Since the top cut plan has to be a couple feet below the floor above (so we don't see sanitary serving the floor above), areas where there's very little space and sanitary serving the floor above and vent serving the floor in question are so close that it's difficult to make sure things display on the level they are supposed to display. This leads us to have to show vent piping lower than it will actually be installed.
- Storm has a similar situation. Since we show storm piping as if there were no cut planes, we often have to show it lower than it will actually be installed so it shows on the correct levels. With it being sloped piping, it often falls below the ceilings in some areas, even though it will all be installed above the ceilings.
9 times out of 10, these are non-issues because the plans look fine. The problem arises in situations like what we are dealing with right now where architects have RCPs and can see our piping below their ceilings. They don't want to just turn the piping off because they do need to see the drops in walls and chases.
I know how I'm handling this right now cannot be the most practical way to do things. This is just the way I was taught many years ago. So my question is, what does everybody else do? Do people have similar issues? Is there some sort of industry standard I'm unaware of? I would love any insight people can give and if anything I said doesn't make sense, let me know and I'll try to elaborate.