When I add a second revision to a sheet, in the revision schedule it shows "varies" instead of populating a second line

chris.hreniuk
Explorer
Explorer

When I add a second revision to a sheet, in the revision schedule it shows "varies" instead of populating a second line

chris.hreniuk
Explorer
Explorer

Revit Revision Schedule.PNG

0 Likes
Reply
Accepted solutions (1)
328 Views
3 Replies
Replies (3)

jay_colcombe
Mentor
Mentor
Accepted solution

This is standard scheduling formatting!

You need to sort by a Field as it is reporting multiple values and hence reads varies!

You could do it by date or number and hide this field if necessary.

This will need to be done in the sheet family if the Revision schedule is embedded in there.

Jay Colcombe

Autodesk Certified Instructor
Revit Architecture & Structure Certified Professional
AutoCAD Certified Professional
B.Sc. Hons Civil & Structural Engineering

If you find my post interesting, feel free to give a Kudo.
If it solves your problem, please click Accept to enhance the Forum.
0 Likes

ToanDN
Consultant
Consultant

ToanDN_0-1699391134732.png

 

0 Likes

chris.hreniuk
Explorer
Explorer

This solved it. Thank you!

 