First establish your levels, like this:
BASEMENT at -8'-11".
T.O. FOOTING at -9'-3"
Then, go to your BASEMENT level floor plan and draw the wall.
(Base constrain = BASEMENT. Top constrain = (next level up) or a numeric positive value if it is Unconnected. Base offset = 0)
Then, on the same BASEMENT level floor plan draw a floor as a 4" concrete slab
(The top of the floor will be placed automatically at the BASEMENT level if you keep the default settings)
Then, on the T.O.FOOTING floor plan draw the continuous footing as a concrete beam, using the center line of the wall as a reference.
(The top of the beam will be placed automatically at the T.O.FOOTING level if you keep the default settings)
That should give you the results you are looking for, as per the image you posted.
Alfredo Medina
info@planta1.com
Alfredo Medina _________________________________________________________________ ______
Licensed Architect (Florida) | Freelance Instructor | Profile on Linkedin