Message 1 of 3
- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
As the title states, I cannot click on the Split & Place button in the Modify/Schedule Quantities Menu for my Lighting Fixture Schedule.
I have created two sheets by the same name to place the sheets in E-002 & E-003 "Lighting Fixture Schedule".
I was able to split and place my Mechanical & Plumbing no problem, I followed the exact same steps for the electrical but the button I need to complete the task is greyed out.
Thanks in advance for anyone that might have any ideas on how to resolve this thanks.
Solved! Go to Solution.