I have just done "Edit Assembly for a wall" as you see the attachment.

I was edited layers by use "Modify Verticel Structure/Split, Reveal,Assign Layer and Modify"

I make Terracotta layer's Top and bottom level. Section view was right but Schedule didn't calculate this top and bottom terracotta level.

Only calc. wall hight (1510mm.) => 1,51mt x 1,00mt. (lenght) = 1,51m2

But it must be this => Total lenght of terracotta (0,36+1,51+0,4)mt x lenght (1,00mt) = 2,27m2

 

Help me  plaese, thank you.

0 个赞
4,237 次查看
14 条回复
回复 (14)
2 条消息(共 15 条)

Anonymous
不适用
Anybody dont know ?
0 个赞
3 条消息(共 15 条)

Alisder.Brown
Collaborator
Collaborator

Hey swstk

 

You are going to have to explain in more detail what you have done and what you are looking to do.

 

It is not very clear from your description or image what the problem is.

 

Thanks

Alisder Brown
Senior BIM Coordinator
Scotland, UK

0 个赞
4 条消息(共 15 条)

Anonymous
不适用

Hi Alisder,

Thank you, for your answer.

 

My problem is simple actually. I want to a wall edit and calculate finish layer area.
Finish layer (like terracotta or aluminium cover) have "top and bottom swap/turn" like attachement.
But schedules calculate area only wall's (length X height => 1000x1510= 1,51m2) area.
Schedules does not calculate "top and bottom swap/turn". (360+400)x1000=0,144m2
Section view is right but calculate is wrong.


Right result => 1,51m2 + 0,144m2 = 1,654m2
Schedule resutl => Only 1,51m2

 

I hope to be describe.

0 个赞
5 条消息(共 15 条)

constantin.stroescu
Mentor
Mentor

I think here is a misunderstand..it is not a return of the finish material on the bottom and on the top of the wall as it seems to be, but a simple different -variable thicknes of the material..

As you can see in my first screen capture , in material Takeof Schedule Areas a not changed but Volume are 

In my second screen capture I used Modify > Unlocked Layer and then moving the arrow of the layer you will see that both Area and Volume are changing..

 

 

Image 1.png

 

 

 

 

Image 2.png

Constantin Stroescu

EESignature

6 条消息(共 15 条)

Anonymous
不适用

Thank you, for your answer Constantin.

 

I understant this method does not run i want to way. 

Your explain very helpfull for how unlock layer work.

 

Well, Is there a different method i want to calculate? I think my section view clear. My wall (or different method) is "C type".

It have "Front+Bottom+Top" measure and i want to calculate (all of them measure) x (total length) = Area.

 

Hoe do you think use method. Wall (does not run), Curtain wall, Generic Model etc.

 

Thanky you.

 

 

0 个赞
7 条消息(共 15 条)

constantin.stroescu
Mentor
Mentor
已接受的解答

A U shaped wall with scheduled Layers can be obtained using Component > Model in Place with Sub Categories , Materials and Parameters.....

The result is something like in the attached file..

Changing parameter values will do changes into Area and Volume values of the wall materials- as can be seen in my screencast:

https://screencast.autodesk.com/Main/Details/a6fd938c-bb58-44df-aee9-6dd5901db38d

 

I'll make a description of the process aftter office time.....

Constantin Stroescu

EESignature

8 条消息(共 15 条)

Anonymous
不适用

Thank you for your answer Constantin,

It is very helpfull. Im happy to be explain for my problem. 😄

 

I will be waiting look forward to your description of the process.

 

Thank you.

 

0 个赞
9 条消息(共 15 条)

constantin.stroescu
Mentor
Mentor
已接受的解答

I've made a screencast on the subject of the C shaped wall. I've considered the hight of the wall between two levels.

The screencast begins with the  already made wall and continues with the construction of it  from scratch....

I hope it will help you...

https://screencast.autodesk.com/Main/Details/21cbbc65-ae14-478e-b9d5-5c4b956bcfb4

 

Constantin Stroescu

EESignature

10 条消息(共 15 条)

Anonymous
不适用

Your work is very helpfull.

Thank you for your attention Master 😄

 

0 个赞
11 条消息(共 15 条)

Anonymous
不适用

I have a question. Material Area calculate's is not work right.
Revit calculate total surface area for a material object.

exp. 1mt x 1mt x 1mt cube single view area' is 1mt2, but revit total material area calculate 1m2 x 6 surface = 6m2

Unfortunately i need to a single/seciton view area.

 

As your project U-wall (attached). "Tile,Mosaic,Gray" 's is Material area is 8,78m2 (as you see project material take off)

 

Finish cover section view is total dimension (70+2,70+70=4,1mt) and wall length (1,0mt)
Use the this dimension and calculate area is 4,1mt x 1,0mt = 4,1m2 Right result. (Not 8,78m2)

 

Have you a solution for this situation, thank you.

0 个赞
12 条消息(共 15 条)

Anonymous
不适用

I have a question. Material Area calculate's is not work right.
Revit calculate total surface area for a material object.

exp. 1mt x 1mt x 1mt cube single view area' is 1mt2, but revit total material area calculate 1m2 x 6 surface = 6m2

Unfortunately i need to a single/seciton view area.

 

As your project U-wall (attached). "Tile,Mosaic,Gray" 's is Material area is 8,78m2 (as you see project material take off)

 

Finish cover section view is total dimension (70+2,70+70=4,1mt) and wall length (1,0mt)
Use the this dimension and calculate area is 4,1mt x 1,0mt = 4,1m2 Right result. (Not 8,78m2)

 

Have you a solution for this situation, thank you.

0 个赞
13 条消息(共 15 条)

constantin.stroescu
Mentor
Mentor

yes,you are right. Revit calculates the area as the whole perimeter of the finish layer multipled with Wall Length

Image 2.png

In order to make a usable area calculation as you want, we need to make a slight adjustment:

  • change parameters into Shared Parameters ( so to be able to list them into schedule)
  • in schedule, make a Calculated Value Field - something like this: [Level Height + 2*(Wdepth+FinThick)]*Length

I'll make a screencast after office time....

 

Constantin Stroescu

EESignature

14 条消息(共 15 条)

Anonymous
不适用
I see and thank you answer.
I was hoping to have a different solution. 🙂
0 个赞
15 条消息(共 15 条)

constantin.stroescu
Mentor
Mentor
已接受的解答
  •  a Field called FinishSurface using the formula : (StrHeight + 2 * StrThick + 2 * StrDepth) * WLengthh  in which the parameters are Shared Parameters will control the surface of the finishes for the Wall created by Model in Place
  • for Basic Walls , the Material Area calculation is OK 
  • for these reasons, I suggest using two different material schedules ( in fact it is the same one but controled by filters)

 

Create Shared Parameters:

Image 4.png

 

Image 5.png

 

Create Calculated Value - FinishSurface:

Image 6.png

 

 

The basic Material Takeoff will look like this:

Image 7.png

 

After Duplicating the schedule and applieng Filter , results two lists - one for Basic Walls and one for special C Walls:

Image 8.png

 

Image 9.png

 

I have attached the work file....

Constantin Stroescu