Schedule can't calculate percentage of counts?

Schedule can't calculate percentage of counts?

CADdaddy.com
Collaborator Collaborator
435 Views
3 Replies
Message 1 of 4

Schedule can't calculate percentage of counts?

CADdaddy.com
Collaborator
Collaborator

Hi all,

 

I'm tantalizingly close to being able to do what I want to do.  I'm trying to create a schedule showing the percentage of King/Queen rooms in a hotel project. 

 

Below I have a Room schedule where I've assigned each type of room (K1, K2, K3, QQ1, QQ2, etc)  to a separate Department and I have a column of the resulting counts.  I though that I would be able to get a percentage of the Count by the Grand Total but the Count field is not available for selection!

 

I'm really disappointed that something this basic is not possible.  Am I missing something?

 

James

 

 

percent.PNG

0 Likes
436 Views
3 Replies
Replies (3)
Message 2 of 4

ToanDN
Consultant
Consultant
Add another Integer parameter to the schedule, sort by it to collapse the schedule to 1 row, enter 1 as the value, re-sort to what you have, and use it to calculale %.
Message 3 of 4

CADdaddy.com
Collaborator
Collaborator

OMG!  You're AWESOME.

0 Likes
Message 4 of 4

christopher_dayW9RUV
Community Visitor
Community Visitor

Likewise, thank-you! @revit please change this so count can be %'d.

0 Likes