Schedule Bottom-up

Schedule Bottom-up

ThijsLugt
Contributor Contributor
2,648 Views
9 Replies
Message 1 of 10

Schedule Bottom-up

ThijsLugt
Contributor
Contributor

For revision schedules you can go to Schedule Properties > Build schedule - Top down/Bottom up

If you go to a normal Schedule (quantity schedule) this option is greyed out.

Is it possible to change this?

 

I have some assemblies on sheets and i want to add a quantity schedule on those sheets, but i want it to expand upwards.

2,649 Views
9 Replies
Replies (9)
Message 2 of 10

mpeperkamp
Collaborator
Collaborator

Hi @ThijsLugt ,

 

Is there a parameter that you can sort by?
Then use the option to select the Ascending or Descending option on the Sorting / Grouping tab.

I hope this can help you further.

 

If my post answers your question, please click the "Accept as Solution" button. This helps everyone find answers more quickly!

Best regards,
Michiel Peperkamp
Cadac Group AEC
Cadac Group
Platinum Partner
Message 3 of 10

ThijsLugt
Contributor
Contributor

I think ascending or descending wont change that it keeps expanding downwards, it only changes the order?

0 Likes
Message 4 of 10

Alan.johnson1970
Advisor
Advisor

This option is only for Revision Schedules and nothing else.

 

AJ.
Message 5 of 10

ThijsLugt
Contributor
Contributor

ah, why limit it to revision schedules only... they should change that.

Thx for the replies.

Message 6 of 10

ThijsLugt
Contributor
Contributor

Any updates for this?

Schedule Properties.PNG

Message 7 of 10

brian_kish54RRL
Explorer
Explorer

This is disappointing that this option is not available for typical schedules, and not just rev block schedules

Message 8 of 10

PierreLucFortin
Explorer
Explorer

Def should!

0 Likes
Message 9 of 10

germanvallverdu
Explorer
Explorer

It's a problem that the orientation of schedules cannot be changed outside of the label family.
I have a client who needs to add more information to the schedules, and it's not possible to add new parameters to a schedules within the Title Blocks family.
It is possible to add them to a revision table created within the project.
Please enable one of the two options.
Or add your own parameters to the schedules within the Title Blocks family.
Or change the creation direction of the schedules even if it's created within the project and not the family.

0 Likes
Message 10 of 10

RSomppi
Mentor
Mentor

The Ideas forum is where Autodesk looks for new feature requests.