If I have a wall with an interior finish layer of Plywood but then I partially split the face and  paint it as Gypsum Board for example, will the panted area be subtracted from the Plywood quantity take off or will I have both the whole Plywood and the Gypsum board? 

I suspect its the latter?  Is there another way of spliting a wall finish for material take offs other than using parts and spliting them?

0 Likes
Accepted solutions (1)
1,726 Views
4 Replies
Replies (4)
Message 2 of 5

alan.johnson7YLND
Advisor
Advisor
Accepted solution

Splitting the face and applying paint will give you as you said "the whole Plywood and the Gypsum board"

 

revit split paint.PNG

 

If you Edit Type for the wall,  split the layer and assign a material then you will get a different result 

 

Revit split wall.PNG

 

 

Message 3 of 5

barthbradley
Consultant
Consultant

Pull the "Material: As Paint" Parameter into the Schedule.  

0 Likes
Message 4 of 5

ToanDN
Consultant
Consultant

@ConstantineC wrote:

If I have a wall with an interior finish layer of Plywood but then I partially split the face and  paint it as Gypsum Board for example, will the panted area be subtracted from the Plywood quantity take off or will I have both the whole Plywood and the Gypsum board? 

I suspect its the latter?  Is there another way of spliting a wall finish for material take offs other than using parts and spliting them?


Paint both areas with different materials: original and paint.

 

ToanDN_3-1682015945019.png

 

 

ToanDN_2-1682015905896.png

 

 

ToanDN_1-1682015793915.png

 

 

ToanDN_0-1682015654917.png

 

0 Likes
Message 5 of 5

ConstantineC
Advocate
Advocate

So another way is to schedule just the paint. Probably this is how its done in a conceptual stage for early estimate?