I have received the output from a colleague which is the site plan view containing toposurface, building pad etc and I need to merge it into the main model that contains the floor plan views (level 1, level 2 etc) but does not have any site plan view. The colleague's model (with the site plan) also contains the building but it is an old version.
I am used to Autocad where it's possible to copy and paste different layers but I can't find anything similar here in Revit
Is there any method to copy the work on the 'site plan' view into the main model? it is only the site view that has been changed as discussed there are no changes to any of the other views/floor plans
Thank you for helping 🙂