- Mark as New
- Bookmark
- Subscribe
- Mute
- Subscribe to RSS Feed
- Permalink
- Report
Hi. I am a civil engineering student. I have been working on a school model as a student project. I am trying to find the total cost of the project. But in some cases, the unit price of a material or element changes with respect to change of floor level. For example, each concrete column construction costs 10,000 BDT for the first 3 floors. But after the 3rd floor, the cost increases by 2,000 BDT for each additional floor. My model has 5 floors. So, I will need to increase the unit price for these additional floors and find out the total cost of the project. This change of unit price also occurs for other concrete members such as beam, slab, etc. I am trying to figure out the best way to deal with this. But still not sure how to do that.
Solved! Go to Solution.