How to get the created mass curb and gutter to report in schedule?

abutlerHQPER
Explorer
Explorer

Any help on this would be greatly appreciated. Trying to get the mass curb and gutter (in red) to report on the schedule. Not sure what I am doing wrong or missing. See attached PDF. will to make available the actual .rvt. Thanks In advance.

0 Likes
354 Views
3 Replies
Replies (3)
Message 2 of 4

ToanDN
Consultant
Consultant

Is it a Mass schedule?

0 Likes
Message 3 of 4

abutlerHQPER
Explorer
Explorer
So, it’s a floor schedule. Trying to capture the square yards for pricing. I was hoping to keep them all floor based. Any suggestions on how to deal with this would be grateful. Thanks
0 Likes
Message 4 of 4

ToanDN
Consultant
Consultant

@abutlerHQPER wrote:
So, it’s a floor schedule. Trying to capture the square yards for pricing. I was hoping to keep them all floor based. Any suggestions on how to deal with this would be grateful. Thanks

Floor schedules don't include masses.  You need to model them as Floors or create a separate mass schedule to pick up the masses.

 

If you only need to get the material data, then create a multi category material take off and it can cover both floors and masses.