FLOOR MATERIAL DOUBLES IN MATERIAL TAKEOFF SCHEDULE

FLOOR MATERIAL DOUBLES IN MATERIAL TAKEOFF SCHEDULE

design01RHDW2
Participant Participant
845 Views
3 Replies
Message 1 of 4

FLOOR MATERIAL DOUBLES IN MATERIAL TAKEOFF SCHEDULE

design01RHDW2
Participant
Participant

Hi everyone, I am trying to make a material takeoff schedule for my floor finishes. However all materials double in quantity when in material takeoff schedule. I checked the model and I have not duplicated any floor/ floor boundary. Hope someone could share some insights on this. Thank you!Screenshot 2024-05-16 104704.pngScreenshot 2024-05-16 105057.png

0 Likes
846 Views
3 Replies
Replies (3)
Message 2 of 4

jay_colc
Mentor
Mentor

You need to filter down where there are applied.  If you select the Blue Row in the Schedule on the right side of the Ribbon "Highlight in Model" you can then see where it is placed to delve further, from the Manage Tab > Inquiry Panel > Id's of Selection and get the number

You can do this for the Yellow Line is should be a different number, you can now use these references number and using Select by ID and find out what's going on

Jay Colcombe

Autodesk Certified Instructor
Revit Architecture & Structure Certified Professional
AutoCAD Certified Professional
B.Sc. Hons Civil & Structural Engineering

If you find my post interesting, feel free to give a Kudo.
If it solves your problem, please click Accept to enhance the Forum.
0 Likes
Message 3 of 4

design01RHDW2
Participant
Participant

Yes, I actually highlighted all of them in the model using the "Highlight in Model" command and I also check the material ID of both and all the doubled areas have the same ID.

0 Likes
Message 4 of 4

jay_colc
Mentor
Mentor

The nature of Material Takeoffs is that each item will show for every material in the family 

 

In the Material Takeoff Schedule, use Sorting and Grouping:
Sorting and Grouping Tab
Sort by Material
Check Grand Totals and Uncheck Itemize every Instance

 

Otherwise you will need to resort to Quantities/Schedules instead of Material Takeoff Schedule

Jay Colcombe

Autodesk Certified Instructor
Revit Architecture & Structure Certified Professional
AutoCAD Certified Professional
B.Sc. Hons Civil & Structural Engineering

If you find my post interesting, feel free to give a Kudo.