hello all
I am trying to figure how this can be a simple solution
I would like to be able to generate a drawing index that will allow us to track all drawings that are part of a submission
if we have 125 drawings in our list (schedule) all have been issued for Permit
we add 5 more drawings for Bid
then add 25 more drawings for Construction
Bulletin 1 only submitting 50 drawings
1. 125 drawings submitted
2.130 drawings submitted
3. 155 drawings submitted
4. 50 drawings submitted
I would like to be able to see the history of each drawing in a list as it relates to its issue.
has anyone had any success in associating the revision schedule to a drawing schedule without adding too much user integration into the workflow?
any help is appreciated.
thank you
If there is any information shared that is of value please give Kudos
If a solution is provided by any posters please mark them as Solved to benefit everyone else.
thank you
Solved! Go to Solution.