Hi all,
In my script I need Dynamo to wait for completed the first part and after that continue with the rest. But I can’t get it accomplished.
In the first part (Blok 1), parameters are filled, after that I need to go further with the schedule (Blok 2) (with the filled in parameters), but the filled parameters don’t come true.
If I run the script the second time, then it runs like is has to be (cause it sees the filled parameters).
Solved! Go to Solution.
Solved by jeremy_tammik. Go to Solution.
Dynamo issues like this are best discussed in the Dynamo forum:
We only know the pure Revit API here, no Dynamo.