How to post the lead-in/out feed rate?

How to post the lead-in/out feed rate?

Anonymous
Not applicable
828 Views
3 Replies
Message 1 of 4

How to post the lead-in/out feed rate?

Anonymous
Not applicable

Hello everyone!

 

I have a problem.

 

I can't output the feed rate of Lead-in/out,It still uses the cutting Feed rate.

 

How should I set it up?

 

Thanking you in advance.

 

 

1.jpg

 

 

0 Likes
Accepted solutions (1)
829 Views
3 Replies
Replies (3)
Message 2 of 4

Sudhira
Autodesk Support
Autodesk Support

@Anonymous wrote:

Hello everyone!

 

I have a problem.

 

I can't output the feed rate of Lead-in/out,It still uses the cutting Feed rate.

 

How should I set it up?

 

Thanking you in advance.

 

 

1.jpg

 

 


 

Hi @Anonymous ,

 

Thanks for posting in Autodesk Community!

 

As I see your query, it's about to set lead in and lead out feed-rate in Lead Feed Rates tab as well as the feed rate should reflect in NC program. As you know this feed rate is calculated in percentage with respect to cutting feed rate and to understand this, I have attached a PowerMill project FYR. In this project, you can see a single slice toolpath and in toolpath connection, extended move is selected in Lead ins & Lead outs move to define the feed-rates. And under the Feed Speed dialog in Lead in and Lead out feed rate, I have set the value in percentage calculation. Finally get the NC program by using default PowerMill post-processor and get the correct result. Please have a look and if anything else related to this query, feel free to reply me. I will be glad to assist you. 

 

If my post answers your query, please click on 'Accept as Solution' button.

 


Thanks,
Sudhira Dora
0 Likes
Message 3 of 4

Anonymous
Not applicable

Thanks so much for response.

I tried the project you provided with my post.

It does read different feed rates.

2.png

 

SO I guess it's a question of strategy.

The strategy I used was 'Drilling-Profile'.

1.png

Can you test it for me again?

Thank you very much!

 

0 Likes
Message 4 of 4

Sudhira
Autodesk Support
Autodesk Support
Accepted solution

@Anonymous wrote:

Thanks so much for response.

I tried the project you provided with my post.

It does read different feed rates.

2.png

 

SO I guess it's a question of strategy.

The strategy I used was 'Drilling-Profile'.

1.png

Can you test it for me again?

Thank you very much!

 


Hi @Anonymous,

 

Apologies for late reply, because of occupied in other tasks. 

 

And thanks for your response. Currently, this functionality is not available for drilling strategy. I can make a wish for you.

 